Summary:
Process Plant engineering design by Tetra Tech progressing; Concentrator and Refinery mechanical design is largely complete
Optimal shipping solution study by Denmark?s Blue Water Shipping complete
Greenland port study by Danish engineering firm Ramboll on schedule for completion in December, 2014
Residue storage facility design by AMEC advancing and set for completion in December, 2014
Assay program on previously drilled cores set for completion in November, 2014
Mine design and scheduling commenced with SRK; outputs to include capital and operating costs for an open‐pit mining operation, and establishment of a mining reserve