Default ASX: GGG progress update

http://www.ggg.gl/docs/ASX-announcem...Oct%202014.pdf

Summary:

Process Plant engineering design by Tetra Tech progressing; Concentrator and Refinery mechanical design is largely complete

Optimal shipping solution study by Denmark?s Blue Water Shipping complete

Greenland port study by Danish engineering firm Ramboll on schedule for completion in December, 2014

Residue storage facility design by AMEC advancing and set for completion in December, 2014

Assay program on previously drilled cores set for completion in November, 2014

Mine design and scheduling commenced with SRK; outputs to include capital and operating costs for an open‐pit mining operation, and establishment of a mining reserve

 